Question

1 Approved Answer

Sewing operators are working in a factory completing 4 operations to sew a skirt. Each operation needs the following times to complete the skirt. Line

Sewing operators are working in a factory completing 4 operations to sew a skirt. Each operation needs the following times to complete the skirt.

Line balancing chart

Operation 1

Operation 2

Operation 3

Operation 4

Sewing Times

1 - 3 min

3- 6 min

1-3 min

6- 12 min

The sewing room has 40 sewists available. Were there any sewists that had to be sent home because they were not needed to create the progressive method sewing lines?

Group of answer choices

none

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing And Assurance Services

Authors: Alvin Arens, Randal Elder, Mark Beasley

14th Edition

1256560812, 9781256560814

More Books

Students also viewed these Accounting questions

Question

What are practice monitoring programs?

Answered: 1 week ago