sh the network schedule given in figure 2 and find the optimum time and the least total cost. Indirect cost = $ 150/day. Activity Duration
sh the network schedule given in figure 2 and find the optimum time and the least total cost. Indirect cost = $ 150/day.
Activity | Duration | Direct Cost ($) | Cost | Day | Cost /day | Days shortened | |||||||
Normal | Crash | Normal | Crash | Cycle 1 | Cycle 2 | Cycle 3 | Cycle 4 | Cycle 5 | |||||
A | 3 | 2 | 500 | 550 | |||||||||
B | 4 | 3 | 300 | 400 | |||||||||
C | 5 | 3 | 200 | 380 | |||||||||
D | 8 | 7 | 700 | 820 | |||||||||
E | 7 | 7 | 300 | 300 | |||||||||
F | 9 | 7 | 200 | 550 | |||||||||
Days cut | |||||||||||||
Project Duration | |||||||||||||
Increased cost/day | |||||||||||||
Total Direct cost | |||||||||||||
Total Indirect cost | |||||||||||||
General Total Cost |
Q. 1. Find the optimum duration.
15 days
18 days
20 days
13 days
Q.2. Find the minimum cost.
$4,590
$4,680
$4,850
$4,120
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started