Shale Remodeling uses time and materials pricing. It is setting prices for next year using the following information: Labor rate, including fringe benefits $ 105
Shale Remodeling uses time and materials pricing. It is setting prices for next year using the following information:
Labor rate, including fringe benefits | $ | 105 | per hour |
Annual labor hours | 6,450 | hours | |
Annual materials purchases | $ | 1,258,750 | |
Materials purchasing, handling, and storage | $ | 251,750 | |
Overhead for depreciation, taxes, insurance, etc. | $ | 741,750 | |
Target profit margin for both labor and materials | 25 | % | |
What is the total price for a project requiring 260 direct labor hours and $250,000 of materials?
Multiple Choice
-
$316,800.
-
$360,000.
-
$436,500.
-
$426,500.
-
$434,000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started