Shale Remodeling uses time and materials pricing. It reports the following information: Direct labor rate $ 80 per DLH Non-materials-related overhead $ 50 per DLH
Shale Remodeling uses time and materials pricing. It reports the following information: Direct labor rate $ 80 per DLH Non-materials-related overhead $ 50 per DLH Materials-related overhead 14% of direct materials cost Target profit margin (both conversion and direct materials) 20% The time charger per hour of direct labor is: