Question
Shamrock Construction Company uses the percentage-of-completion method of accounting. In 2020, Shamrock began work under contract #E2-D2, which provided for a contract price of $2,156,000.
Shamrock Construction Company uses the percentage-of-completion method of accounting. In 2020, Shamrock began work under contract #E2-D2, which provided for a contract price of $2,156,000. Other details follow:
2020 | 2021 | |||
Costs incurred during the year | $598,290 | $1,421,000 | ||
Estimated costs to complete, as of December 31 | 1,018,710 | 0 | ||
Billings during the year | 425,000 | 2,156,000 | ||
Collections during the year | 357,000 | 1,497,000 |
(a) | What portion of the total contract price would be recognized as revenue in 2014? In 2015? |
(b) | Assuming the same facts as those above except that Hamilton uses the completed-contract method of accounting, what portion of the total contract price would be recognized as revenue in 2015? |
(c) | Prepare a complete set of journal entries for 2014 (using the percentage-of-completion method). |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started