Sharon's team used a chart to track all the planned activities in order to identify how well they were progressing and point out any delays
Sharon's team used a chart to track all the planned activities in order to identify how well they were progressing and point out any delays or deviations from the original plan. This chart, which includes a listing of all the activities with columns for planned and actual schedules, is referred to as a Group of answer choices PERT chart. grading chart. Gantt chart. tracking chart