Sheffield Manufacturing Company uses a standard cost accounting system. In 2022, 28,000 units were produced. Each unit took several kilograms of direct materials and 1.6
Sheffield Manufacturing Company uses a standard cost accounting system. In 2022, 28,000 units were produced. Each unit took several kilograms of direct materials and 1.6 standard hours of direct labour at a standard hourly rate of $15.00. Normal capacity was 48,500 direct labour hours. During the year, 117,600 kg of raw materials were purchased at $0.95 per kilogram. All materials purchased were used during the year.
If the materials price variance was $5,880 favourable, what was the standard materials price per kilogram? (Round answer to 2 decimal places, e.g. 5.25.)
Standard price per kilogram = | $enter the standard price per kilogram in dollars rounded to 2 decimal places |
If the materials quantity variance was $5,600 unfavourable, what was the standard materials quantity per unit? (Round answer to 2 decimal places, e.g. 5.17.)
Standard materials quantity per unit= | enter the standard materials quantity per unit in kilograms rounded to 2 decimal places | kilograms |
What were the standard hours allowed for the units produced?
Standard hours allowed= | enter the standard hours allowed |
If the labour quantity variance was $9,300 unfavourable, what were the actual direct labour hours worked?
Actual direct labour hours = | enter the actual direct labour hours |
If the labour price variance was $18,168 favourable, what was the actual rate per hour? (Round answer to 2 decimal places, e.g. 15.25.)
Actual rate per hour= | $enter the actual rate per hour in dollars rounded to 2 decimal places |
If total budgeted manufacturing overhead was $392,850 at normal capacity, what was the predetermined overhead rate? (Round answer to 2 decimal places, e.g. 15.25.)
Predetermined overhead rate= | $enter the predetermined overhead rate in dollars rounded to 2 decimal places |
What was the standard cost per unit of product? (Round intermediate calculations and final answer to 2 decimal places, e.g. 1.25.)
Standard cost per unit= | $ enter the standard cost per unit in dollars rounded to 2 decimal places |
How much overhead was applied to production during the year?
Overhead applied= | $enter the overhead applied in dollars |
Using selected answers above, what were the total costs assigned to work in process? (Round answer to the nearest whole dollar, e.g. 5,275.)
Total costs assigned to work in process | = | $ enter the total costs assigned to work in process in dollars rounded to the nearest whole |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started