Sheridan Company has a materials price standard of $4 per pound. 5000 pounds of materials were purchased at $4.20 a pound. The actual quantity of
Sheridan Company has a materials price standard of $4 per pound. 5000 pounds of materials were purchased at $4.20 a pound. The actual quantity of materials used was 5000 pounds although the standard quantity allowed for the output was 3600 pounds. Sheridan Company's materials price variance is
$1000 U.
$280 U.
$1000 F.
$1440 U.