Sheridan Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed-price contract for $2.4 million beginning September 1, 2023, to build

Sheridan Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed-price contract for $2.4 million beginning September 1, 2023, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2025. The following data pertain to the construction period. 2023 Costs to date Estimated costs to complete 5656,000 1,394,000 Progress billings to date (non-refundable) 708,000 Cash collected to date 556,000 2024 $1,452.000 968,000 1,968,000 1.851.000 2025 $2,018,000 0 2.400,000 2,400,000 (a) Using the percentage-of-completion method, calculate the percentage complete for 2023 and 2024. (Round answers to 2 decimal places, e.g. 52.75%.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Auditing An Integrated Approach

Authors: Richard Cascarino

3rd Edition

1485110599, 978-1485110590

More Books

Students also viewed these Accounting questions

Question

model flow of liquid in python code correctly

Answered: 1 week ago