Sheridan Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable

Sheridan Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $10.0 million. The following data pertain to the construction period.

2020 2021 2022
Costs for the year $3,510,000 4,290,000 1,900,000
Estimated costs to complete 4,290,000 1,950,000 -0-
Progress billings for the year (non-refundable) 3,185,000 3,715,000 3,100,000
Cash collected for the year 2,805,000 3,765,000 3,430,000

1.

Using the percentage-of-completion method, calculate the percent complete for each year of the contract.

2020 2021 2022
Percent complete

2.Calculate the amount of the gross profit to be recognized each year of the contract. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

2020 2021 2022

gross profit

3.

Prepare the journal entries for 2020 and 2021. (Use Materials, Cash, Payables for costs incurred to date.) (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.) For Year 2020:

Account Titles and Explanation

Debit

Credit

(To record cost of construction)

(To record progress billings)

(To record collections)

(To record revenues)

(To record construction expenses)

For Year 2021:

Account Titles and Explanation

Debit

Credit

(To record cost of construction)

(To record progress billings)

(To record collections)

(To record revenues)

(To record construction expenses)

4.What is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021?

December 31, 2020 December 31, 2021
Balance in the Contract Asset/Liability account $ $

5.Show how the construction contract would be reported on the SFP and the income statement for the year ended December 31, 2021. (List Current assets in order of liquidity. Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45))

SHERIDAN ENTERPRISES LTD. Partial Statement of Financial Position Month Ended December 31, 2021December 31, 2021Quarter Ended December 31, 2021
select an opening name for subsection one Current AssetsIntangible AssetsCurrent LiabilitiesLong-term LiabilitiesProperty, Plant and EquipmentShareholders' EquityTotal AssetsTotal Current AssetsTotal Current LiabilitiesTotal LiabilitiesTotal Liabilities and Shareholders' EquityTotal Long-term LiabilitiesTotal Property, Plant and EquipmentTotal Shareholders' Equity
$

SHERIDAN ENTERPRISES LTD. Partial Income Statement Year Ended December 31, 2021Month Ended December 31, 2021Quarter Ended December 31, 2021
$
select a summarizing line for the first part Income from OperationsExpensesRevenuesTotal RevenuesDividendsGross Profit / (Loss)Operating ExpensesOther Expenses and LossesTotal ExpensesNet Income / (Loss) $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing That Matters Case Studies

Authors: Norman David Marks

1st Edition

B089J17FFW, 979-8650160410

More Books

Students also viewed these Accounting questions

Question

=+ Which stakeholder needs will be met and satisfied?

Answered: 1 week ago