Shine Company uses a predetermined overhead rate of $15.00 per machine hour. The rate was based on estimated total manufacturing overhead cost of $390,000 and
Shine Company uses a predetermined overhead rate of $15.00 per machine hour. The rate was based on estimated total manufacturing overhead cost of $390,000 and estimated machine hours of 26.000. Shine incurred actual total manufacturing overhead costs of 5374,000 and total machine hours of 22,000. The total amount of overhead applied to all jobs during the period would be closest to: QA $374.000 CA $300.000 OC $442.000 OD $330,000