Question
Shoney Video Concepts produces a line of video streaming servers that are linked to personal computers for storing movies. These devices have very fast access
Shoney Video Concepts produces a line of video streaming servers that are linked to personal computers for storing movies. These devices have very fast access and large storage capacity.
Shoney is trying to determine a production plan for the next 12 months. The main criterion for this plan is that the employment level is to be held constant over the period. Shoney is continuing in its R&D efforts to develop new applications and prefers not to cause any adverse feelings with the local workforce. For the same reason, all employees should put in full workweeks, even if that is not the lowest-cost alternative. The forecast for the next 12 months is
MONTH | FORECAST DEMAND | MONTH | FORECAST DEMAND |
January | 600 | July | 200 |
February | 800 | August | 200 |
March | 900 | September | 300 |
April | 600 | October | 700 |
May | 400 | November | 800 |
June | 300 | December | 900 |
Manufacturing cost is $200 per server, equally divided between materials and labor. Inventory storage cost is $5 per month. A shortage of servers results in lost sales and is estimated to cost an overall $20 per unit short.
The inventory on hand at the beginning of the planning period is 200 units. Ten labor hours are required per server. The workday is eight hours.
Develop an aggregate production schedule for the year using a constant workforce. For simplicity, assume 22 working days each month except July, when the plant closes down for three weeks vacation (leaving seven working days). Assume that total annual production capacity is greater than or equal to total annual demand (i.e., compute workforce level based on annual demand and annual capacity). (Leave no cells blank - be certain to enter "0" wherever required. Indicate monthly shortages using a negative ending inventory level. Round up the "number of workers" to the next whole number and round down your "monthly production rates" to the nearest whole number.)
January | February | March | April | May | June | July | August | September | October | November | December | Total | |
Forecast | 600 | 800 | 900 | 600 | 400 | 300 | 200 | 200 | 300 | 700 | 800 | 900 | |
Beginning inventory | |||||||||||||
Available production | |||||||||||||
Ending inventory | |||||||||||||
Costs | Total | ||||||||||||
Lost sales | |||||||||||||
Inventory | |||||||||||||
Total | |||||||||||||
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started