Shop order 8989 is for 600 pieces of part 03-298-15. From the routing file it is found that operation 20 s done on work center
- Shop order 8989 is for 600 pieces of part 03-298-15. From the routing file it is found that operation 20 s done on work center 400. The set up time is 3.5 hours and the run time is .233 hours per piece. What is the required capacity on work center 400 for shop order 8989?
Step by Step Solution
There are 3 Steps involved in it
Step: 1