Question
show all answers with working Question 1 (2 Marks) A1, B1, B3 Which of the options below are true for Environmental Management Accounting? Effective management
show all answers with working
Question 1 (2 Marks) A1, B1, B3
Which of the options below are true for Environmental Management Accounting?
- Effective management of environmental costs could be a source for obtaining a competitive advantage
- Environmental costs should be treated as production overheads
- Both above
- None of the above
Question 2 (2 Marks) A1, B1, B3, C1, D1
Which of the following should not be included in an environmental cost budget?
- Cleaning up contaminated sites
- Fines for environmental contamination
- Using methods and technology to prevent pollution
- Systems to detect pollution
Question 3 (2 Marks) C1, D1
Sunny Co manufactures and sells suitcases. Currently sales are 2,000 units at a selling price of $147. Market research has established that for every $30 increase in price, sales will fall by 400 units.
Calculate the demand function for Sunny.
- p = 147 0.075Q
- p = 297 0.075Q
- p = 297 0.030Q
- p = 147 0.030Q
Question 4 (2 Marks) C1, D1
Which of the options below are true for information systems?
- Key features of Enterprise Resource Planning systems (ERPs) are that they are IT systems that integrate the information requirements of different processes or functions within the organisation.
- Passwords can be used to control the level of access to information.
- Both above
- None of the above
Question 5 (2 Marks) C1, D1
Salmon Co has been investigating the time taken for production. During this investigation it found that to produce one of its products, a 90% learning curve appears to be applicable. The time taken for the first unit is 7 hours.
Calculate the total time taken for units 5 to 8 only (in hours).
- 20.142 hours
- 19.590 hours
- 18.144 hours
- 17.078 hours
Question 6 (2 Marks) C1, D1
Product Kleen is manufactured through a production process where the machine time is the bottleneck resource. One unit of Kleen requires 0.6 machine hours. The costs and selling price of Product Kleen are as follows:
| $ |
Materials | 30 |
Labour (0.5 hour) | 18 |
Other factory costs | 2 |
Total | 50 |
Sales price | 64 |
Profit | 9 |
|
|
Given that throughput accounting is followed, what is the throughput accounting ratio for Product Kleen? (Round to 1 decimal place).
- 1.3
- 28.3
- 1.7
- 16.7
Question 7 (2 Marks) C1, D1
Alpha is preparing a standard cost card for Xavy, a new product. Labour is paid at 20 per hour. Batch 1 took 90 hours, and an 80% learning rate is expected. This is expected to cease after 45 batches have been produced.
What is the labour cost per unit that should be included in the standard cost card for Xavy, to the nearest ?
- 18
- 360
- 528
- 1,800
Question 8 (2 Marks) C1, D1
Which of the options below are true for throughput accounting?
- Labour and material costs are not included in total factory costs
- Products that are within the same factory could be ranked based on their return per hour as the cost per hour
- Both above
- None of the above
Question 9 (2 Marks) C1, D1
The standard direct material cost per unit for a product is calculated as follows: 10.5 litres at $2.50 per litre. No inventory of material is held. Last month the actual price paid for 12,000 litres of material used was 4% above standard and the direct material usage variance was $1,815 favourable.
What was the adverse direct material price variance for last month?
a. | $1,000 |
b. | $1,260 |
c. | $1,212 |
d. | $1,200 |
|
|
Question 10 (2 Marks) C1, D1
Last month a company budgeted to sell 8,000 units at a price of $12.50 per unit. Actual sales last month were 9,000 units giving total sales revenue of $117,000.
What was the sales price variance for last month?
- $4,000 favourable
- $4,500 adverse
- $4,000 adverse
- $4,500 favourable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started