show all calculations, preferably in an EXCEL file.Each problem is of equal value.Each part of a problem is equal. A project has just completed its
show all calculations, preferably in an EXCEL file.Each problem is of equal value.Each part of a problem is equal.
A project has just completed its 87th item in the project plan. It was scheduled to have spent $300,000at this point in the plan, but has actually spent only $250,000. The project manager estimates that the value of the work actually finished is nearly $200,000.What are the spending and schedule variances for the project? What are the SPI and CPI?What is the Critical Ratio?
a.CV =
b.SV =
c.SPI =
d.CPI =
e.CR =
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started