show all calculations, preferably in an EXCEL file.Each problem is of equal value.Each part of a problem is equal. A project has just completed its

show all calculations, preferably in an EXCEL file.Each problem is of equal value.Each part of a problem is equal.

A project has just completed its 87th item in the project plan. It was scheduled to have spent $300,000at this point in the plan, but has actually spent only $250,000. The project manager estimates that the value of the work actually finished is nearly $200,000.What are the spending and schedule variances for the project? What are the SPI and CPI?What is the Critical Ratio?

a.CV =

b.SV =

c.SPI =

d.CPI =

e.CR =

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Environmental Regulation Law Science And Policy

Authors: Robert V. Percival, Christopher H. Schroeder, Alan S. Miller, James P. Leape

9th Edition

1543826164, 978-1543826166

More Books

Students also viewed these Law questions