Show how to use Excel to answer the following: The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has
Show how to use Excel to answer the following: The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects. Each costs $6,500 and has an expected life of 3 years. Annual project cash flows begin 1 year after the initial investment and are subject to the following probability distributions:
Project A Project B
Probability | Cash Flows | Probability | Cash Flows |
0.2 | $5,750 | 0.2 | $0 |
0.6 | $6,500 | 0.6 | $6,500 |
0.2 | $7,250 | 0.2 | $19,000 |
BPC has decided to evaluate the riskier project at 12% and the less-risky project at 8%.
a)What is each project's expected annual cash flow? Round your answers to two decimal places.
b) Project B's standard deviation (B) is $6,185.47 and its coefficient of variation (CVB) is 0.80. What are the values of (A) and (CVA)? Round your answers to two decimal places.
c) Based on the risk-adjusted NPVs, which project should BPC choose, project A or project B?
d) If you knew that Project B's cash flows were negatively correlated with the firm's other cash flow, but Project A's cash flows were positively correlated, how might this affect the decision. Would this make project B more or less appealing?
e) If Project B's cash flows were negatively correlated with gross domestic product (GDP), while A's cash flows were positively correlated, would that influence your risk assessment. Would this make project B more or less appealing?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started