Shown below are 15 data points relating to the Receiving cost and tons of material for Acme Manufacturing Receiving Tons of Observation Cost Material 1
Shown below are 15 data points relating to the Receiving cost and tons of material for Acme Manufacturing Receiving Tons of
Observation Cost Material
1 $67,100 47,300
2 75,200 68,200
3 92,200 93,500
4 88,600 79,200
5 87,700 96,800
6 80,200 49,500
7 98,000 73,700
8 67,600 40,700
9 68,500 46,200
10 78,500 63,800
11 71,700 50,600
12 80,300 48,400
13 78,000 55,000
14 80,000 69,300
15 93,800 53,900
Required: a. Using the High-Low method, determine the cost equation for receiving costs. (4 pts)
b. Use the equation in part a. to estimate receiving costs when the tons of material are estimated to be 65,000. (3 pts)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started