Sierra Mountain bikes SMB needsto develop a large new supply chain management system within 24 months and an available budget of $8,200,000. The full set
Sierra Mountain bikes SMB needsto develop a large new supply chain management system within 24 months and an available budget of $8,200,000. The full set of capabilities adds up to 200 KSLOC of software. Beaver, Inc. is a CMMI Level 3 company, is generally familiar with the product line, will follow general conformity in design flexibility, generally does architecture and risk resolution, and has a largely cooperative team (i.e., all of its scale factors are rated High). Its average labor cost is $10,000, per person-month. For simplicity, consider all of its baseline cost driver ratings to be Nominal.
Compute the project's cost and schedule for the following cases:
1. Everything as described above, and RELY rated as Nominal
2. RELY rated as High
3. RELY rated as High, SCED rated as Low
How many of “Cost, Schedule, Quality” criteria do the cases satisfy?
Step by Step Solution
3.36 Rating (152 Votes )
There are 3 Steps involved in it
Step: 1
1 The projects cost would be 8200000 and the schedule would be 24 m...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started