Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $112,800. Overhead is

  1. Single plantwide factory overhead rate

    Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $112,800. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit:

    Budgeted Production Volume Direct Labor Hours Per Unit
    Flutes 2,200 units 0.4
    Clarinets 800 1.5
    Oboes 1,400 1.2

    If required, round all per unit answers to the nearest cent.

    a. Determine the single plantwide overhead rate. $fill in the blank 1 per direct labor hour

    b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products.

    Total Factory Overhead Cost Per Unit Factory Overhead Cost
    Flutes $fill in the blank 2 $fill in the blank 3
    Clarinets fill in the blank 4 fill in the blank 5
    Oboes fill in the blank 6 fill in the blank 7
    Total $fill in the blank 8

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Lost Continent The BBCs Europe Editor On Europes Darkest Hour Since World War Two

Authors: Gavin Hewitt

1st Edition

1444764829, 9781444764826

More Books

Students also viewed these Accounting questions