Question

1 Approved Answer

Situation 1: WBS Element BCWS (PV) BCWP (EV) ACWP (AC) P $1,000 $1,100 $1,150 Q $2,000 $1,800 $2,100 R $1,000 $1,200 $1,050 S $2,000 $1,900

Situation 1:

WBS Element

BCWS (PV)

BCWP (EV)

ACWP (AC)

P

$1,000

$1,100

$1,150

Q

$2,000

$1,800

$2,100

R

$1,000

$1,200

$1,050

S

$2,000

$1,900

$1,800

Using Situation 1 above, which WBS element is behind schedule but under budget?

Element P

Element Q

Element R

Element S

Using Situation 1 above, which WBS element has a favorable cost variance of $150?

Element P

Element Q

Element R

Element S

Using Situation 1 above, the cost performance index (CPI) for WBS element R is

0.875 1.14 0.952 0.833 1.20

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Larry P. Ritzman, Manoj K. Malhotra

10th edition

978-013280747, 132807394, 9780132951814, 132807475, 132951819, 978-0132807395

More Books

Students also viewed these General Management questions