Question
Situation: You are the Project Manager at an industrial complex. You are expecting to spend a total of $58,000 on your existing project. When you
Situation:
You are the Project Manager at an industrial complex. You are expecting to spend a total of $58,000 on your existing project. When you checked the plan, you find out that it says "Six people working on the project eight hours a day, five days a week for five weeks". When you checked the schedule, you find out that your team has just finished the third week of the project. Upon careful review, you see that the team has completed 51% of the work, at a cost of $27,000.
Questions:
- Calculate the Earned Value. (9 points)
PV =
EV =
CV =
BAC =
AC =
SV =
SPI =
CPI =
- Check all of the following that apply:
The project is ahead of schedule
The project is behind schedule
You should consider crashing the schedule
The project is over budget
The project is under budget
You should find a way to cut costs (6 points).
3. You must show the formulas you used from the text book.(3 Points)
I need all the references too.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started