Situation - You find the ASDG peer review of your CMPT to have been a huge success as you have received numerous relevant suggestions for
Situation - You find the ASDG peer review of your CMPT to have been a huge success as you have received numerous relevant suggestions for improving your CMPT.
Assignment - According to the PMBOK Guide, "The Schedule Performance Index (SPI) is a measure of schedule efficiency, expressed as the ratio of earned value to planned value."
The Schedule Performance Index gives you information about the schedule performance of the project. It is the efficiency of the time utilized in the project.
- The formula for the Schedule Performance Index (SPI)
- The Schedule Performance Index can be determined by dividing earned value by planned value.
- Schedule Performance Index = (Earned Value) / (Planned Value)
In a in Word doc, explain how the Schedule Performance Index is performing addressing directly to the DIT COO, Program Manager, and Project Managers in the project. Utilize project scope cost, estimation, and budget information to connect how the formula is applied.
In conclusion to your paper, use information gathered from your EVM and PV reports and CMPT, perform the Schedule Performance Index (SPI), and provide the results: SPI= EV / PV
Submit your work for review and grading.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started