Question

1 Approved Answer

Sitwell Construction is constructing an office building for Bluth Company and uses the percentage-of completion method. The contract calls for progress billings and payments of

Sitwell Construction is constructing an office building for Bluth Company and uses the percentage-of completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Sitwell estimates total costs of $17,750,000. Sitwell estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. The building was 30% complete at the end of 2021.

At December 31, 2022 Sitwell construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $18,000,000 due to unanticipated price increases. What is the total amount of construction expenses that Sitwell will recognize for the year ended December 31, 2022?

a. $13,500,000

b. $7,875,000

c. $7,987,500

d. $8,175,000

Please show all work! TY in advance :)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Business Mathematics In Canada

Authors: F. Ernest Jerome, Jackie Shemko

3rd Edition

1259370151, 978-1259370151

Students also viewed these Accounting questions