Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as following
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as following table.
Job | Operation 1 (Hours) | Operation 2 (Hours) |
A | 10 | 5 |
B | 7 | 4 |
C | 5 | 7 |
D | 3 | 8 |
E | 2 | 6 |
F | 4 | 3 |
- Determine the sequence that will minimize the total completion time for the jobs using Johnsons rule.
- Illustrate graphically the throughput time and idle time at the two operations by constructing a time-phased chart.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started