Six jobs must be processed through machine A and then B as shown below. The processing time for each job is also shown. Machine (minutes)
Six jobs must be processed through machine A and then B as shown below. The processing time for each job is also shown.
Machine (minutes)
JOB | A | B |
1 | 10 | 6 |
2 | 6 | 12 |
3 | 7 | 7 |
4 | 8 | 4 |
5 | 3 | 9 |
6 | 6 | 8 |
a. Develop a Gantt chart to determine the total time required to process all six jobs. Use the following sequence of jobs: 1, 2, 3, 4, 5, 6
b. Can you develop a better sequence to reduce the total time required for processing?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started