Skold Company produce s s lacks. Materials for the s l ac ks are dyed in lar ge vats . After d ye ing the

Skold Company produces slacks. Materials for the slacks are dyed in large vats. After dyeing the materials for a given colour, the vats must be cleaned and prepared for the next batch of materials to be coloured. The following standards for changeover for a given batch have been established:

Direct materials (2.5 kg @ $1.20) _______ $ 3

Direct labour (0.40 hr. @ $16.00) _______ $ 6.40

Standard prime cost _________________ $ 9.40

During the year, 79.500 kilograms of material were purchased and used for the changeover activity. There were 30,000 batches produced, with the following actual prime costs:

Direct materials _________$ 86,800

Direct labour ____________173,850 (for 11,400 hrs.)

Required:

  1. Compute the materials and labour variances associated with the changeover activity, labelling each variance as favourable or unfavourable.
  2. Find the total material variance and total labour variance labelling each variance as favourable or unfavourable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Paul M. Fischer, William J. Tayler, Rita H. Cheng

11th edition

978-0538480284

Students also viewed these Accounting questions