______ slack measure assumes that all noncritical tasks will be started at their latest starting times and can be interpreted as the maximum time by
______ slack measure assumes that all noncritical tasks will be started at their latest starting times and can be interpreted as the maximum time by which a task's duration can be exceeded without causing a delay in the project. A. Total B. Free C. Safety D. Independent