Question
Smith Excavation and Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2021 and was completed in 2022. Data relating to the
Smith Excavation and Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2021 and was completed in 2022. Data relating to the construction are:
2021 2022
Costs incurred during the year $3,300,000 $2,750,000
Estimated costs to complete 2,700,000
Dalton uses the percentage-of-completion method.
Instructions
(a) How much revenue should be reported for 2021? Show your computation.
(b) Make the entry to record progress billings of $4,100,000 during 2021.
(c) Make the entry to record the revenue and gross profit for 2021.
(d) How much gross profit should be reported for 2022? Show your computation.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started