Question
Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct
Snavely, Inc., manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below:
Expected Production | Direct Labor-Hours Per Unit | Total Direct Labor-Hours | |
Product E1 | 600 | 8.0 | 4,800 |
Product A7 | 300 | 4.0 | 1,200 |
Total direct labor-hours | 6,000 | ||
The direct labor rate is $24.90 per DLH. The direct materials cost per unit for each product is given below:
Direct Materials Cost per Unit | |||
Product E1 | $206.00 | ||
Product A7 | $225.00 | ||
The company has an activity-based costing system with the following activity cost pools, activity measures, and expected activity:
Estimated | Expected Activity | |||||
Activity Cost Pools | Activity Measures | Overhead Cost | Product E1 | Product A7 | Total | |
Labor-related | DLHs | $ | 109,600 | 4,800 | 1,200 | 6,000 |
Machine setups | setups | 51,690 | 700 | 300 | 1,000 | |
Order size | MHs | 808,470 | 2,800 | 3,500 | 6,300 | |
$ | 969,760 | |||||
The activity rate for the Order Size activity cost pool under activity-based costing is closest to:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started