Question
Sofia Romano worked as a corporate reliability engineer for Regal Electronics Inc. (REI), a global company selling hundreds of namebrand products in more than 53
Sofia Romano worked as a corporate reliability engineer for Regal Electronics Inc. (REI), a global
company selling hundreds of namebrand products in more than 53 countries. Sofia was curious about a
new product announcement from Molio Equipment Manufacturing Inc. (MEMI), a supplier of advanced
manufacturing equipment and components. REI had a longstanding relationship with another supplier,
Decker Products Ltd. (DPL) for much of REIs production equipment. MEMI claimed that their new
equipment had undergone a complete redesign and was now capable of manufacturing product with
greater speed and quality.
Sofia had done extensive testing with DPLs equipment over the past 6 years and worked with DPL and
REI staff to optimize the setup, maintenance, training, processes, etc. As a result, over the past 2 years
average profit was reliably about $6,000 per production run. In translating what MEMIs claim of
improved speed and quality meant for REIs product line, Sofia calculated there was a 10% chance of
reaching a whopping $20,000 average profit per production run, 60% chance of obtaining $5,000
average per run, 20% chance of securing $10,000 average profit per run, and a 10% chance of no profit
at all for a given run. Note that MEMI was willing to match DPLs purchase price for the equipment.
According to MEMI, uncertainty was based on a combination of variables such as how the equipment
was setup, operated, maintained, quality and combination of raw materials used, and many other
factors. Sofia spoke at great length to MEMI about the improved potential of the new equipment, but
was hesitant to take on any increased risk. Eventually, MEMI offered, for a fixed fee of $2500, to
provide consulting services in order to show REI how to accurately predict the average profit before
each run (i.e., the four possibilities calculated above by Sofia) based on REIs anticipated mix of variables
for that run. Depending on results, Sofia could then choose to run production through the new MEMI
equipment, or the DPL equipment on another line, on an offshift, at another site, etc. Given that Sofia
had to replace the DPL production equipment on one of 10 production lines in one facility, timing
couldnt be better. She would either go with the new MEMI equipment, or simply replace the
equipment with another DPL unit.
(a) Should Sofia consider purchasing MEMIs equipment? Should she pay for MEMIs consulting
services?
(b) What other factors should be considered in determining whether to switch to MEMIs equipment?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started