1 Approved Answer

SOFTWARE PROJECT MANAGEMENT Given the following COCOMO constants table: Application a b c d Organic 2.4 1.05 2.5 0.38 Semi-Detached 3.0 1.12 2.5 0.35 Embedded

SOFTWARE PROJECT MANAGEMENT

Given the following COCOMO constants table:

Application

a

b

c

d

Organic

2.4

1.05

2.5

0.38

Semi-Detached

3.0

1.12

2.5

0.35

Embedded

3.6

1.20

2.5

0.32

The project is about developing smart home device. A person on your team who has done this before estimates the total lines of code to be 100K LOC. The software requires very high reliability, with high complexity and memory constraint. Team members are known with high analyst capability and some of them are highly experienced of the application. The team is also very fluent in the software tools used in the system development. All other factors can be considered to be nominal.

a) Calculate the total effort (E) needed for this project.

b) Calculate the total duration (D) of this project in months.

c) Calculate the suggested number of team members (P).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Probabilistic Databases

Authors: Dan Suciu, Dan Olteanu, Christopher Re, Christoph Koch

1st Edition

3031007514, 978-3031007514

More Books

Students also viewed these Databases questions

Question

1. Write down two or three of your greatest strengths.

Answered: 1 week ago

Question

What roles have these individuals played in your life?

Answered: 1 week ago

Question

2. Write two or three of your greatest weaknesses.

Answered: 1 week ago