Solve the below using Winters Mathematical Modelling. Dont use CHATGPT or AI. Show me calculations: Table-2.1 Costs and other information Item Cost Material cost 15/unit
Solve the below using Winters Mathematical Modelling. Dont use CHATGPT or AI. Show me calculations:
Table-2.1 Costs and other information
Item | Cost |
Material cost | 15/unit |
Inventory holding cost | 0.3/unit/month |
Marginal cost of stockout/backlog | 25/unit |
Hiring and training cost | 1000/worker |
Layoff cost | 2000/worker |
Labour hours required | 3 hours/unit |
Regular time cost | 6/hour |
Overtime cost | 12/ hour |
Cost of subcontracting | 38/unit |
Starting workforce size | 100 |
Overtime limitation per worker | 10 hours/month |
Initial inventory | 1000 units |
End inventory | 1000 units |
Shift | 1 |
Hours per day | 8 |
Days per month | 4 weeks * 5 days |
Selling price | 40/unit |
Table-2.2 Demand Forecast of 2020
Forecast | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
2020 | 5,000 | 3,000 | 4,000 | 3,000 | 7,000 | 6,000 | 8,000 | 11,000 | 20,000 | 20,000 | 22,000 | 8,000 |
The operational data of costs and other information of South West Electronics (SWE) Ltd are provided in table-2.1. Using the demand forecast given in table-2.2, make an aggregate production plan of 2020 for SWE. Please specify how you build your planning model with necessary calculation progress included and conclude your forecasting results.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started