Soon after award of a CPFF contract to the contractor for development of research, Dan was named the NASA resident project engineer for technical administration
Soon after award of a CPFF contract to the contractor for development of research, Dan was named the NASA resident project engineer for technical administration of the contract. His scope of authority was outlined in the following contractual provisions: (1) The Resident Project Engineer may issue directions (which include, but are notlimited to, redirecting Contractor's effort, shifting of emphasis on work areas andsuspending work of a research and development type) to the Contractor without thenecessity of submitting these directions through the Contracting Officer if suchdirections are within the overall scope of work and rate of effort and within the funds provided for in the contract. (2) Assist the Contractor in interpreting technical phases of contract drawings, specifications, or other purchase description. (3) Assist the Contractor in obtaining such technical data as may be needed by theContractor and which may be made available to the Contractor by or through theContracting Officer or the Stage Engine Contractor. (4) Review the technical reports submitted by the Contractor in accordance withcontract terms and notify the Contracting Officer of acceptance or nonacceptance when approval is required. (5) Perform technical acceptance of all specifications, and modifications to specifications, including top assembly drawings, as prepared by the Contractorpursuant to contract terms. (6) Initiate requests for preliminary engineering data necessary to keep the Government and/or the associated contractors currently informed of the developmentstatus and problem areas, prior to the issuance by the Contractor of formalinformation. (7) Direct the Contractor to deliver any prototype and/or research and developmenthardware items in the state of completion existing at the time delivery is specified inthe directions.The parties hereto agree that the maximum benefits obtainable from the work to be performed hereunder will be realized only by the Contractor's pursuing a programwhich is flexible and capable of adaption to changing conditions, and by providingfor an extensive exchange of information between the Contractor and theGovernment as a basis for periodic revisions of the program through changes inapproach to the problem. The work to be conducted under this contract shall be under the technical direction of the Resident Project Engineer assigned by the Administration, whose duties and authority are delineated in ARTICLE VI. The Contractor shall permit representatives of the Resident Project Engineer and Contracting Officer to inspect the work at any time and place during working hours. The Contractor may communicate directly with theResident Project Engineer on technical aspects of the work being performed.Projects, and project approach aspects within the scope of this contract, will be authorized directly by the Resident Project Engineer to the Contractor in accordancewith ARTICLE VI. The Resident Project Engineer does not have the authority toauthorize projects or project approaches which would entail additional funds or any changes in the scope of work under this contract. Resident Project Engineer'sInstructions hereunder may be either written or ratified by him in writing.Several months after the contract started, it was discovered that the necessary heat-resistant properties specified for the material to be used were beyond the capacity of anything yedeveloped. Mr. Wilson held a conference with Western engineers to discuss the problem, and, after several hours, they reached a decision to conduct additional research in the area of heat resistance to determine whether or not the specification could be met. Since the decision waspurely a technical one, Mr. Wilson authorized Western to proceed. The company's engineers ran into difficulties almost immediately, but, after severalattempts, were able to develop an alloyed material that would withstand the specifiedtemperature. A few weeks later, contractor submitted a $138,000 voucher for the work, most of which was attributable to the highly skilled labor that had been used in developing the new, more heat-resistant material. When compared to the overall work completed on the contract, this voucher made a cost overrun of some $125,000 imminent. After reviewing the history of the contract with contractor, the NASA contracting officer said he believed that Mr. Wilson had overstepped his authority when he told the company to conduct original research. He stated that he did not feel that the NASA was obligated to pay for the research.
does mr Wilson have the authority to make this decision and is the contract entilited to an equitable adjustment? why or why not?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started