Question
Southeast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following demand
Southeast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following demand forecast: Q1 1,800, Q2 1,100, Q3 1,600, Q4 900
COSTS/OTHER DATA |
---|
Previous quarter's output = 1,300 cases |
Beginning inventory = 50 cases |
Back-Order cost = $150 per case |
Inventory holding cost = $40 per case at end of quarter |
Hiring employees = $40 per case |
Terminating employees = $80 per case |
Subcontracting cost = $60 per case |
Unit cost on regular time = $30 per case |
Overtime cost = $15 extra per case ($45) |
John's job is to develop an aggregate plan. The three initial options he wants to evaluate are:
a. Plan A: a strategy that hires and fires personnel as necessary to produce the current period's forecast. Include any costs due to the change in the production level from the previous output level. Total cost = $ [ Select ] ["314,000", "325,000", "315,000", "$322,000", "315,575"] . What was the total inventory holding cost? $8,000
b. Plan B: a level strategy, producing an average demand rate. Include any costs due to the change in the production level from the previous output level. Cost = $ [ Select ] ["329,000", "259,500", "$308,500", "328,500", "327,000"] . Was there a need to back-order units? [ Select ] ["back-ordering is not an option in this case", "no, there was no need to back-order", "yes"] . If so, how many units and what was the total back-ordering cost? [ Select ] ["1200 units; $180,000", "400 units; $60,000", "$150", "zero, no need to backorder, all demand levels were met with regular time production", "950 units; cost $142,500"]
c. Plan C: a level strategy that produces 1,200 cases per quarter and meets the forecast demand with inventory and subcontracting (your subcontractor only has the capacity to fill a maximum of 300 units per quarter). Include any costs due to the change in the production level from the previous output level. Total Cost = $ [ Select ] ["225,750", "222,000", "220,567", "330,237", "$257,500"]
d. Which strategy is the lowest-cost plan?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started