Speedrat Company manufactures specialised gaming mice. It has provided the following information so that overhead costs could be assigned to each job: Activity Name Overhead
Speedrat Company manufactures specialised gaming mice. It has provided the following information so that overhead costs could be assigned to each job:
Activity Name | Overhead Cost $ | Activity Driver |
Material handling | 12,000 | 30,000 units |
Machining | 38,000 | 2,000 machine hours |
Packing | 10,000 | 8,000 packing orders |
The company received a job order S11 from a customer that had the following production details:
Direct material | $37,000 |
Direct labour | $9,400 |
No of units to be produced | 6,000 |
No of machine hours | 700 |
No of packing orders | 2,000 |
(Round up all the answers to 2 decimal places if necessary)
(a) Using machine hours as the basis of allocating overheads, compute:
(i) the plantwide overhead rate per machine hour.
(ii) the total overhead cost assigned to job order S11.
(b) Using the associated activity driver, calculate the activity rate for:
(i) Material handling.
(ii) Machining.
(iii) Packing.
(c) Calculate the unit product cost for job order S11 using activity-based costing.
(d) Briefly explain why activity-based cost assignment is more accurate than a single plantwide overhead rate.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started