Question
Speedy-Go, Inc., produces custom-built engines for automobile race teams. The most recent project undertaken by Speedy-Go requires 14 different activities. Speedy-Go's sponsor would like to
Speedy-Go, Inc., produces custom-built engines for automobile race teams. The most recent project undertaken by Speedy-Go requires 14 different activities. Speedy-Go's sponsor would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table. What is the probability of being done in 53 days? ________
Your answer should be carried out to three decimal places.
Activity | Immediate Predecessor(s) | Optimistic Time | Most Likely Time | Pessimistic Time |
A | - | 4 | 6 | 7 |
B | - | 1 | 2 | 3 |
C | A | 6 | 6 | 6 |
D | A | 5 | 8 | 11 |
E | B,C | 1 | 9 | 18 |
F | D | 2 | 3 | 6 |
G | D | 1 | 7 | 8 |
H | E,F | 4 | 4 | 6 |
I | G,H | 1 | 6 | 8 |
J | I | 2 | 5 | 7 |
K | I | 8 | 9 | 11 |
L | J | 2 | 4 | 6 |
M | K | 1 | 2 | 3 |
N | L,M | 6 | 8 | 10 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started