Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Spilker Construction Company had a contract starting April 2023, to construct a $34,500,000 building that is expected to be completed in September 2025, at an

Spilker Construction Company had a contract starting April 2023, to construct a $34,500,000 building that is expected to be completed in September 2025, at an estimated cost of $28,570,000. At the end of 2023, the costs to date were $9,250,000 and the estimated total costs to complete had not changed. The progress billings during 2023 were $8,505,000 and the cash collected during 2023 was 4,500,000. The company uses the percentage-of-completion method.

At December 31, 2023 Spilker would report Revenue from Long-Term Contracts in the amount of:

Question 25 options:

a)

$11,169,933

b)

$9,250,000

c)

$1,919,933

d)

$5,930,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamental Accounting Principles

Authors: Larson Kermit, Tilly Jensen

Volume I, 14th Canadian Edition

71051503, 978-1259066511, 1259066517, 978-0071051507

Students also viewed these Accounting questions

Question

=+5. For the cost matrix of Exercise 3,

Answered: 1 week ago