Sta. Clara Construction Company has used the cost to cost percentage of completion method of recognizing revenue. In reviewing the records, Sta. Clara finds the
Sta. Clara Construction Company has used the cost to cost percentage of completion method of recognizing revenue. In reviewing the records, Sta. Clara finds the following information regarding a recently completed building project for which the total contract was P20,000,000.
Gross profit (loss) Cost incurred
2017 400,000 3,600,000
2018 1,400,000 ?
2019 (200,000) 8,200,000
Sta. Clara wants to know how effectively the company operated during the last 3 years on this project and, since the information is not complete, has asked you to analyze the project as to the amount of revenue, costs, gross profit and percentage of completion recognized during the 3 years.
a.How much is the contract revenue during 2017?
b.What is the percentage of completion in 2017?
c.How much is the cost incurred in 2018?
d.What is the percentage of completion in 2018?
e.How much is the total estimated cost to complete in 2018?
f.How much is the total estimated gross profit in 2018?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started