Question
1 Approved Answer
Standard 1 2 3 4 Forecast 3000 3500 5000 4000 Projected Available 2000 3000 1500 500 500 MPS 4000 2000 4000 4000 Lot Size 2000
Standard | 1 | 2 | 3 | 4 | |
Forecast | 3000 | 3500 | 5000 | 4000 | |
Projected Available | 2000 | 3000 | 1500 | 500 | 500 |
MPS | 4000 | 2000 | 4000 | 4000 | |
Lot Size | 2000 | ||||
Deluxe | |||||
Forecast | 2000 | 1500 | 1000 | 3000 | |
Projected Available | 2000 | 1000 | 2500 | 2500 | 500 |
MPS | 1000 | 3000 | 1000 | 1000 | |
Lot Size | 1000 | ||||
Capacity | 5000 | 5000 | 5000 | 5000 |