Standard Cost Profile Lab Treatment SU #12 Expected Treatments = 1,000 Quantity Quantity Unit Variable Average Average Resource Variable Fixed Cost Cost Fixed Cost Total

Standard Cost Profile

Lab Treatment SU #12

Expected Treatments = 1,000

Quantity Quantity Unit Variable Average Average

Resource Variable Fixed Cost Cost Fixed Cost Total Cost

Labor 0.80 0.80 $ 16.00 $ 12.80 $ 12.80 $ 25.60

Supplies 7.00 0 1.10 7.70 0 7.70

$ 20.50 $ 12.80 33.30

Actual Month Cost

Lab Treatment SU #12

Actual Treatments = 1,100

Quantity Unit Total

Resource Used Cost Cost

Labor 1,600 $ 17.00 $ 27,200

Supplies 7,500 1.00 7,500

$ 34,700

Calculate the following variances:

Price Variance Supplies

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions