Question

1 Approved Answer

Standard wage rate is Rs . 2 per hour and standard time is 1 0 hours. But actual wage rate is Rs . 2 .

Standard wage rate is Rs.2 per hour and standard time is 10 hours. But actual wage rate is Rs.2.25 per hour and actual hours used are 12 hours.Calculate Labour cost variance.

Step by Step Solution

There are 3 Steps involved in it