Question
Star Construction Corporation has a contract to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract.
Star Construction Corporation has a contract to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $8,850,000. Construction commenced on 4 February 20×5. Actual costs were in line with estimated costs for 20×5 and 20×6. In 20×7, actual costs exceeded estimated costs by $150,000.
Total construction costs incurred in each year were as follows:
20X5: $2,700,000
20X6: $4,500,000
20X7: $1,800,000
Progress billings based on the amount of work completed were collected each year. Star Construction uses the percentage-of-completion method. The percentage-of-completion is based on costs incurred compared with estimated total costs of the project.
Company also billed the client and collected the following payments
Year | Billings | Payments Received |
20X5: | $2,300,000 | $2,100,000 |
20X6: | $4,900,000 | $4,700,000 |
20X7: | $3,750,000 | $4,150,000 |
Required:
Calculate Net income for the construction project for each of the three years:
a) Completed contract method?
20X5: $______________ 20X6: $__________________ 20X7____________________.
b) Percentage-of-completion method? (basis: estimated costs to complete)
20X5: $______________ 20X6: $__________________ 20X7____________________.
Step by Step Solution
3.45 Rating (161 Votes )
There are 3 Steps involved in it
Step: 1
a Completed contract method 20X5 0 20X6 0 20X7 1950000 The total profit on the contract will be reco...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started