Question

1 Approved Answer

State the validity along with respective reasons: 1.Resource leveling aims at smooth of the resource usage rate without changing the project duration 2.Two activities have

State the validity along with respective reasons:

1.Resource leveling aims at smooth of the resource usage rate without changing the project duration

2.Two activities have common predecessor and successor activities. So, they can have common initial and final nodes

3.In respect of any activity whether real or dummy, the terminal node should bear a number higher than the initial node number

4.The optimal duration of a project is the minimum time in which it can be completed

Assume that A is the activity which has a successor named as S

5.Amount of time by which the actual completion of A can exceed its earliest expected time of completion without any delay of the project

6.Latest start time minus earliest start time of A

7.Value by which A can be delayed beyond its earliest start point without affecting earliest start time of S

8.Latest finish time of A minus earliest start time of S

Roma Ltd has $25,700 in cash with the issue of common stock dated Jan 1, Year 1.

The proceeds was used to purchase equipment for $25,700 and had a salvage value of $4,500 with 4 years life.

In the beginning of 5th year, equipment was being sold for $4,980.

Revenue:

Year1=7,480

Year2=7,980

Year3=8,180

Year4=6,980

Year5=0

Compute:

A.Income Statement for each of the five years

B.Statement of changes in Stockholder's equity for each of the five years

C.Balance sheet for each of the five years

D.Statement of cash flows for each of the five years

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting Volume 2

Authors: Thomas Beechy, Joan Conrod, Elizabeth Farrell, Ingrid McLeod-Dick

6th Edition

1259105482, 9780071338820

More Books

Students also viewed these Accounting questions