Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Status of a work package for a project has following values. What is the Cost Variance (CV) for this work package? PV = $500,000 EV

Status of a work package for a project has following values. What is the Cost Variance (CV) for this work package?

PV = $500,000 EV = $350,000 AC = $550,000 BAC = $1,200,000

a.

-$150,000

b.

$900,000

c.

-$200,000

d.

-$50,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

12th Edition

1119165350, 9781119165354

More Books

Students also viewed these General Management questions

Question

=+a. Does it flow? (Can anyone read it out loud without stumbling?)

Answered: 1 week ago

Question

=+e. Does it use simple language, not technical jargon?

Answered: 1 week ago