Status of a work package for a project has following values. What is the Estimate to Complete (ETC) for this work package? PV = $500,000
Status of a work package for a project has following values. What is the Estimate to Complete (ETC) for this work package?
PV = $500,000 EV = $350,000 AC = $550,000 BAC = $1,200,000
a.
$850,000
b.
$1,050,000
c.
$700,000
d.
$900,000