Status of a work package for a project has following values. What is the Estimate to Complete (ETC) for this work package? PV = $500,000

Status of a work package for a project has following values. What is the Estimate to Complete (ETC) for this work package?

PV = $500,000 EV = $350,000 AC = $550,000 BAC = $1,200,000

a.

$850,000

b.

$1,050,000

c.

$700,000

d.

$900,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

13th Edition

1119805376, 978-1119805373

More Books

Students also viewed these General Management questions

Question

What does this public think about this issue?

Answered: 1 week ago

Question

What benefits can you offer this public?

Answered: 1 week ago

Question

How free does this public see itself to act on this issue?

Answered: 1 week ago