Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Step 1: Complete the Risk Management Plan Template below. Step 2: Read the Fast Delivery Parts Store scenario below. Then, : a). Identify at least

Step 1: Complete the Risk Management Plan Template below.

Step 2: Read the Fast Delivery Parts Store scenario below. Then, :

a). Identify at least two risks to the project in addition to the three identified in the scenario below. Note: You may use some creative license while identifying additional risks.

b). Using the Risk Management Plan Template, fill out the Risk Assessments for each of the five (or more) risks identified. Be sure to provide complete information for each of the risks associated with this project. Note: You may use some creative license while completing the risk assessments.

c). Fill out a Probability Impact Matrix for each of the risks identified in the previous steps by identifying the risk impact level for cost, schedule, scope, and quality. Use the Risk Impact Chart below.

d). Based on your analysis, rank the risks based on their probability of occurrence (from Step 3) and their impact (from Step 5).

SCENARIO:

Fast Delivery Parts Store Scenario Addition

For the Fast Delivery Parts project, (i) you are worried that you do not have trained IT personnel to complete the information system development and changes to the existing information systems. This is definitely a risk that you have planned for. Another risk is (ii) lack of coordination from the suppliers. Despite the earnestness of Shanghai Auto Parts and Rio Parts Company, they are facing resource constraints and have not been able to commit dedicated personnel to the project you are managing. Their involvement is the key for addressing the data inconsistency problem. Yet another risk is that (iii) Fast Delivery Parts has a matrix organizational structure, and there has not been much commitment of resources from functional managers to your project. Without the resource assurances, you may be unable to complete the project in a timely manner.

Risk Impact Chart The following chart shows risk impact definitions across cost, schedule, scope, and quality. During risk analysis, the potential impact of each risk should be analyzed, and an appropriate impact level (e.g., 0.05, 0.10. 0.20, 0.40, or 0.80) should be selected from the chart below (see definitions below).

Project Objective Very Low 0.05 Low 0.10 Moderate 0.20 High 0.40 Very High 0.80
Cost Insignificant cost impact < 10% cost impact 1020% cost impact 2040% cost impact > 40% cost impact
Schedule Insignificant schedule impact < 5% schedule impact 510% schedule impact 1020% schedule impact > 20% schedule impact
Scope Barely noticeable Minor areas impacted Major areas impacted Changes unacceptable to sponsor Product becomes effectively useless
Quality Barely noticeable Only very demanding applications impacted Sponsor must approve quality reduction Quality reduction unacceptable to sponsor Product becomes effectively useless

Risk Management Plan :

Risk #1 Assessment

Risk Description:

Reasons for this risk (i.e., what are the origins of this risk?):

Likelihood of risk occurring (express this as a probability between 0 and 1):

Potential impact on the project:

Ways to address this risk:

Risk #1 Probability Impact Matrix

Project Objective

Very Low

0.05

Low

0.10

Moderate

0.20

High

0.40

Very High

0.80

Cost

Schedule

Scope

Quality

Risk #2 Assessment

Risk Description:

Reasons for this risk (i.e., what are the origins of this risk?):

Likelihood of risk occurring (express this as a probability between 0 and 1):

Potential impact on the project:

Ways to address this risk:

Risk #2 Probability Impact Matrix

Project Objective

Very Low

0.05

Low

0.10

Moderate

0.20

High

0.40

Very High

0.80

Cost

Schedule

Scope

Quality

Risk #3

Risk Description:

Reasons for this risk (i.e., what are the origins of this risk?):

Likelihood of risk occurring (express this as a probability between 0 and 1):

Potential impact on the project:

Ways to address this risk:

Risk #3 Probability Impact Matrix

Project Objective

Very Low

0.05

Low

0.10

Moderate

0.20

High

0.40

Very High

0.80

Cost

Schedule

Scope

Quality

Risk #4

Risk Description:

Reasons for this risk (i.e., what are the origins of this risk?):

Likelihood of risk occurring (express this as a probability between 0 and 1):

Potential impact on the project:

Ways to address this risk:

Risk #4 Probability Impact Matrix

Project Objective

Very Low

0.05

Low

0.10

Moderate

0.20

High

0.40

Very High

0.80

Cost

Schedule

Scope

Quality

Risk #5

Risk Description:

Reasons for this risk (i.e., what are the origins of this risk?):

Likelihood of risk occurring (express this as a probability between 0 and 1):

Potential impact on the project:

Ways to address this risk:

Risk #5 Probability Impact Matrix

Project Objective

Very Low

0.05

Low

0.10

Moderate

0.20

High

0.40

Very High

0.80

Cost

Schedule

Scope

Quality

Rank Project Risks Base

Rank Project Risks Based on their probability of occurrence and their impact.

  1. [Risk needing the greatest amount of attention]
  2. [Risk needing the least amount of attention]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Management

Authors: Andrew J. DuBrin

9th Edition

538478233, 2900538478235, 978-0538478236

More Books

Students also viewed these General Management questions