Question

1 Approved Answer

Step 1 : Timeline The EMS project is scheduled to start on April 3 0 , 2 0 2 1 , and end on July

Step 1: Timeline
The EMS project is scheduled to start on April 30,2021, and end on July 21,2021, spanning a total of 12 weeks. The following Gantt chart provides a visual representation of the project schedule:
Week Task Start Date End Date
1 Requirements Gathering April 30,2021 May 7,2021
2 Design May 8,2021 May 21,2021
3 Development May 22,2021 June 18,2021
4 Testing June 19,2021 June 25,2021
5 Deployment June 26,2021 July 2,2021
6 Training and Support July 3,2021 July 9,2021
7 User Acceptance Testing July 10,2021 July 16,2021
8 Finalization and Handover July 17,2021 July 21,2021
Step 2: Milestones
The following are the key milestones and deliverables for the EMS project:
Requirements Gathering: Completion of a detailed requirements document outlining the system's functionality and features.
Design: Completion of a detailed design document outlining the system's architecture, user interface, and database schema.
Development: Completion of the system's codebase and integration with required third-party services.
Testing: Completion of functional, integration, and user acceptance testing.
Deployment: Deployment of the system to a production environment.
Training and Support: Provision of training and support to end-users.
User Acceptance Testing: Completion of user acceptance testing and sign-off by stakeholders.
Finalization and Handover: Finalization of the system, including documentation and handover to the client.
Step 3: Roles and Responsibilities
The following are the roles and responsibilities for the EMS project:
Project Manager: Overall responsibility for project planning, execution, and delivery.
Business Analyst: Responsible for gathering and documenting project requirements.
Designer: Responsible for designing the system's user interface and database schema.
Developer: Responsible for developing the system's codebase and integrating with third-party services.
Tester: Responsible for testing the system's functionality and ensuring quality.
Trainer: Responsible for providing training and support to end-users.
Step 4: Risk Management
The following are potential risks and mitigation strategies for the EMS project:
Technical Risks:
Mitigation Strategy: Conduct thorough research and testing before implementing new technologies.
Schedule Risks:
Mitigation Strategy: Develop a detailed project schedule and monitor progress regularly.
Resource Risks:
Mitigation Strategy: Ensure adequate resources are available and plan for contingencies.
Quality Risks:
Mitigation Strategy: Implement a robust testing and quality assurance process.
Stakeholder Risks:
Mitigation Strategy: Communicate regularly with stakeholders and manage expectations.expand this answer

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Databases Organizing Information Digital And Information Literacy

Authors: Greg Roza

1st Edition

1448805929, 978-1448805921

More Books

Students also viewed these Databases questions