Question
Step One: Use the data below, hand draw an AON network diagram and calculate Forward Pass, Backward Pass, Slack Time and Critical Path.Clearly identify your
Step One:
Use the data below,hand drawan AON network diagram and calculate Forward Pass, Backward Pass, Slack Time and Critical Path.Clearly identify your critical path.
Step Two:
You have only 16 days to complete this project.What is the least cost solution to achieve completion in 16 days?
Redraw a second AON network diagramby handshowing completion of the network in 16 days and calculate Forward Pass, Backward Pass, Slack Time and Critical Path(s).
Step Three:
What is the least cost increase to achieve the 16 day duration?Hand write your calculations. Show your calculations to arrive at the least cost increase to complete in 16 days.
ActivityPrecedingDurationMax CrashSlope
IDActivityin DaysTime.
ANone31$20
BA52$60
CA31$40
DA100$0
EB63$50
FC73$100
GD,E,F51$70
Step Four:
- Submit the two hand drawn AON networks diagrams (Steps 1 and 2) along with your hand written calculations your name and signature,
- Scan them and place them in a Word document, and submit them to the the Dropbox.
*Please ensure your handwriting is legible
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started