Stephanie wants to record actual hours worked by a resource on a task. How should she do this? A By using the Resource Sheet view.
Stephanie wants to record actual hours worked by a resource on a task. How should she do this? A By using the Resource Sheet view. B By using the Resources button on the Project Guide. C By using the Resource Usage View. D By using the task tab