Question
1 Approved Answer
Stringer Co. expected to make 26,000 units this year but it actually made 27,500 units. the standard price for direct materials is $6.50 per ounce,
Stringer Co. expected to make 26,000 units this year but it actually made 27,500 units. the standard price for direct materials is $6.50 per ounce, and one output unit should use 8 ounces of direct material. Stringer bought 240,000 ounces this year for $1,584,000, but it used only 228,000 ounces in production. The standard price for direct labor is $22 per hour, and one output unit should use 6.6 hours of direct labor. The actual labor hours used this year was 183,000 hours, which cost $4,018,680.
a. What is the direct material quantity (usage) variance?
b. What is the direct labor price (rate) variance?
c. What is the direct labor quantity (time or efficiency) variance?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started